Contractor to testify in Tongaat probe
Updated | By sibahle motha
Gralio Precast is the developing company behind the construction of the mall.
The commission of inquiry was appointed following the structural collapse of the mall on November 19 2013, which claimed the lives of two people and injured 29 others.
In December Tongaat Mall engineer Dr Andre Ballack dismissed suggestions that he was "grossly negligent" by allowing deviations from his drawings Ballack argued that he had no reason to doubt the integrity of the contractor, Singh, who assured him
that the project was proceeding as per specifications until the fatal day.
He has testified that Singh failed on several occasions to furnish him with test cube results to determine the strength of the concrete.
Ballack told the commission that he relied on the contractor's word to authorise the stripping.
The inquiry was expected to complete its work in the first quarter of 2015.

(File photo: Gallo Images)
Show's Stories
-
Does your relationship pass the ‘777 Rule’?
Relationship experts and dating coaches have shared their opinions on th...
The Drive with Rob & Roz 37 minutes ago -
Superstar singer makes brutal dig at her exes while performing
Not many artists would take a break during their Las Vegas residency con...
The Drive with Rob & Roz an hour ago