Eskom: Power system stable today
Updated | By sibahle motha
"If anything unexpected happens, we may need to go into load shedding, but as the situation stands, we are fine at this stage," its media desk said.
Last Monday, Eskom said unit six at its newly-built Medupi power station in Limpopo produced power for the first time.
"The electricity flowing into the grid marks a new beginning," Eskom chief executive Tshediso Matona said in a statement.
"Within the next three months, South Africa will see Medupi unit six's full potential of 794MW being fed into the South African national grid."
This was the first of Medupi power station's six units to be synchronised. Synchronisation, or first power, involves the generator being connected to the grid so its power is aligned with all the other generators to deliver electricity.
(File photo: Gallo images)
Show's Stories
-
"Is that my ear?" Barber pranks kid during haircut
Could you ever get tired of a good prank?
The Workzone with Alex Jay 9 hours ago -
Toddler says he's allowed to bite people
A little boy answers "yes" when asked: "Are you allowed to bite people?"
The Workzone with Elana Afrika-Bredenkamp 9 hours ago