Eskom says it will implement stage 3 load shedding from 5am to 4pm on Thursday which will then be followed by stage 4 power cuts from 4pm to 5am on Friday.

Eskom: Stage 6 load shedding to continue until Friday
iStock

From there stage 3 load shedding will be implemented until 5am on Saturday.


Stage 2 load shedding will be in place on Sunday. 


In a statement, the power utility says further breakdowns have reduced to 15 089MW of generating capacity while the generating capacity out of service for planned maintenance has increased to 7 147MW.


Over the past 24 hours a generation unit was returned to service at Duvha Power Station.


In the same period, a generating unit each at Lethabo, Kendal and Kriel power stations were taken offline for repairs. 


The delays in returning a unit to service at Hendrina, Medupi and two units at Tutuka power stations have contributed to the capacity constraints.